Kersfield Estate, Lytton Grove, SW15
Description
The scheme completed in May 2024. Demolition of existing electricity substation and erection of seven blocks across the estate ranging from two to four-storeys to provide 41 new residential units, together with a new electricity substation.
The scheme also included improvements to the hard and soft landscaping around the new developments and existing buildings on the estate.
Site details
Ward | East Putney |
---|---|
Status | Complete |
Number of units | 41 |
Tenure mix | Council rent |
Unit mix | 14 x 1-bed units 25 x 2-bed units 2 x 3-bed units (including 1 fully wheelchair-accessible unit) |
Planning reference | 2018/5553 |
Images
Consultation events
Three separate pre-planning resident and stakeholder consultation events were undertaken at nearby venues in July 2016 and July and October 2018. We have also conducted a virtual Meet the Contractor event on 2 December 2020 and the presentation slides can be viewed online.
Documents
- Letter to residents - October 2024
- Letter to residents - June 2024
- Letter to residents - May 2024
- Letter to residents - September 2023
- Letter to residents - June 2023
- Letter to residents - October 2022
- Newsletter - August 2022
- Newsletter - December 2021
- Letter to residents - September 2021
- Newsletter - July 2021
- Newsletter - February 2021
- Newsletter - July 2020
- Letter to residents - May 2020
- Letter to residents - October 2018
- Consultation boards - October 2018
- Letter to residents - July 2018
- Consultation boards - July 2018
- Letter to residents - July 2016
- Consultation boards - July 2016
- Letter to residents - January 2015
Contact
For any queries contact the Development Team:
Email: 020 8871 6358
Telephone: developmentteam@wandsworth.gov.uk