Residential development of 106 new Council Rent homes within the Surrey Lane estate. The development comprises three blocks, ranging from four to six storeys, together with associated landscaping and environmental improvements.

News

Hill are continuing to make good progress on the development, moving towards a completion in spring 2025:

  • Block A – Evelyn Dove House – is split into two cores: the scaffolding has now come down and snagging of the new homes is well underway
  • Blocks B and C – Lammas House and Saklatvala House – are both mostly complete and are undergoing the last finishing touches before being ready to hand over
  • Externally, Hill’s landscaping team are making very good progress installing the new features to the public realm, both in the new courtyards and the open space between Evelyn Dove and Lammas House. Hill will continue these works throughout February and March, with completion of the development expected in early spring

Site details

Randall Close 
Ward St Mary's Park
Status Under construction
Number of units 106 Council rent homes
Unit mix 42 x 1-bed flats
57 x 2-bed flats
5 x 3-bed flats
2 x 4-bed flats
Planning reference 2020/0635
Start on site 21 September 2022
Anticipated completion Spring 2025

Resident and stakeholder engagement

  • First event held 4 December 2018 at Randall Close Day Centre from 6 to 8pm
  • Second event held 29 January 2019 at Randall Close Day Centre from 6 to 8pm
  • Third event held 24 April 2019 at Randall Close Day Centre from 4 to 8pm
  • Meet the Contractor event held at the Don Bosco centre on 13 July 2022
  • Meet the Artist event held at the Don Bosco centre on 1 December 2022